Stewart Lake Park – Pedestrian Path
Approximate Construction Timeline
All durations and dates are approximate, based on the availability of material (e.g. crushed stone and the porous asphalt) and in particular on the weather. Updates will be provided if part(s) of the project gets delayed by 2 or more days.
May 23 – June 6
Approximately 2 weeks.
Excavate for and install the crushed stone base course for the portion of the path from the access drive at N. Bayard Ave to the parking lot at Cooper Street.
 
June 6 – June 10
Approximately 1 week.
Excavate for and install the crushed stone base course for the portion of the path on the north bank of the lake behind the YMCA and water treatment plant. 1
 
June 13 – June 17
Approximately 3-4 days.
Construct the terraced walkway to connect the path to the sidewalk on Evergreen Avenue.
 
June 20 – June 24
Approximately 1 week.
Install the porous pavement for the path from the terraced walk to the parking lot. 
 
June 27 – June 29
Approximately 2-3 days.
Install the porous pavement for the path along the north bank of the lake. 
 
June 30 – July 8
Approximately 1 week.
Construct the parking lot expansion and widened driveway at Cooper Street. 
 
July 8 – July 15
Approximately 1 week.
Restoration/turf repair.  